STATS Group provided hot tapping and plugging operations at five locations on a 30” Carbon Dioxide pipeline operating at 153 bar. The project facilitated safe installation of valves and pigging launchers/receivers into a previously unpiggable pipeline, while production was maintained through a 24” temporary bypass. Safely isolating high pressure C02 poses many challenges. To overcome these extensive testing, appropriate material selection and verification trials were conducted.
If you do not have audio on your laptop then join by voice on +44 203 443 9992 and enter code 6275321#